Suggested Answer:Answer: D is incorrect. The project management plan defines all of the processes, activities, and work for the project manager, project management team, and the🗳️
Activity List is created by decomposing Work Breakdown Structure into work packages. These work packages are decomposed into activities and further into smaller tasks that result into the documented activity list. team members. The network diagram clearly shows the relationship of activities, predecessor activities, and successor activities.