Question #: 163
Topic #: 1
[All CCBA Questions]

The RGQ Organization utilizes a change log. What is a change log?

  • A. It is a document that tracks all unauthorized changes to the project solution.
  • B. It is a document that records all change requests for the project.
  • C. It is a document that tracks the changes that have been received, including their implementation to the project solution.
  • D. It is a document that tracks all characteristics and status of changes that have been received.
Show Suggested Answer Hide Answer
Suggested Answer: Answer: A is incorrect. The change log tracks change requests and its status. 🗳️
A change log tracks all characteristics of a proposed change request and it status. into the project.

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
17b7c4c
1 month, 1 week ago
Selected Answer: D
D. It is a document that tracks all characteristics and status of changes that have been received.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...