Suggested Answer:Answer: B is incorrect. Although, the Manage Stakeholders Expectations process helps in closing the project, it is not the prime purpose of this process.🗳️
The prime purpose of the Manage Stakeholders Expectations process is to resolve issues. These issues may be from different areas of the project. An issue log or action item log can be used to document and monitor the resolution of issues. It can be used to facilitate communication and ensure a common understanding of issues. Issues are resolved to maintain good, constructive working relationships among various stakeholders, including team members. Description, category, cause, probability of occurring, impact on objectives, proposed responses, owner, and the current status of all identified risks are put in the risk register. Updating risk registers is done throughout the project duration. It is not the prime purpose of the Manage Stakeholders Expectations process.
The prime purpose of the Manage Stakeholder Expectations process is to address and resolve issues that arise from conflicting stakeholder expectations, ensuring alignment with project goals and fostering stakeholder buy-in. This process focuses on maintaining productive collaboration and mitigating misunderstandings or disagreements that could derail the initiative.
BABOK Reference (Chapter 2: Business Analysis Planning and Monitoring - Manage Stakeholder Collaboration):
Resolving issues is critical to keeping stakeholders engaged and ensuring their expectations remain realistic and aligned with the project’s objectives.
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
teletee
2 weeks ago17b7c4c
5 months, 2 weeks ago