Question #: 506
Topic #: 1
[All CCBA Questions]

A government agency has initiated a project to implement a customer registry that will be shared across multiple agencies. Early estimates indicate there will be hundreds of requirements. While determining the requirements traceability approach, what factor takes precedence?

  • A. Number of stakeholders
  • B. Cost of tracing
  • C. Number of defects
  • D. Cost of testing
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
keyss
2 days, 23 hours ago
Selected Answer: B
B. Cost of tracing
upvoted 1 times
...
17b7c4c
1 month, 1 week ago
Selected Answer: B
BABOK Section 5.1.7: Plan Business Analysis Information Management, it is recommended that the cost of tracing requirements should be carefully considered, particularly in projects with a large number of requirements. Tracing requirements across multiple agencies and stakeholders can be resource-intensive, so it is important to assess the cost and feasibility of maintaining traceability throughout the project. Given the scale and complexity indicated by the hundreds of requirements, managing the cost of tracing takes precedence to ensure that traceability remains practical and within budget.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...