Exam CCBA topic 1 question 486 discussion

Actual exam question from IIBA's CCBA
Question #: 486
Topic #: 1
[All CCBA Questions]

The business analysis deliverables went through a formal performance review process. The performance report stated that changes to the business analysis approach must be made in order to maximize the project's chances of success. Who must be consulted regarding these changes before they are implemented in this project?

  • A. The enterprise architect
  • B. The project manager
  • C. The lead developer
  • D. The subject matter expert
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
17b7c4c
3 months ago
Selected Answer: B
Section 3.1.6: Business Analysis Performance Improvements suggests that changes to the business analysis approach should be considered in the context of the overall project plan, which is managed by the project manager. Effective collaboration with the project manager ensures alignment with project objectives and constraints.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago