Exam CCBA topic 1 question 472 discussion

Actual exam question from IIBA's CCBA
Question #: 472
Topic #: 1
[All CCBA Questions]

A business owner has marked certain requirements as high priority for the upcoming release. After performing some analysis, the project team concluded that some of these requirements are not actually high priority and can be implemented in later releases. How should the project team proceed with prioritizing requirements?

  • A. Consult with the business owner to discuss possible trade-offs
  • B. Execute the requirements that the business owner identified
  • C. Implement the requirements that the project team considers important
  • D. Change the priority of the requirements by performing a re-ranking
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
keyss
1 day, 3 hours ago
Selected Answer: A
A. Consult with the business owner to discuss possible trade-offs
upvoted 1 times
...
17b7c4c
1 month, 1 week ago
Selected Answer: A
Section 5.3.5: Prioritize Requirements highlights that prioritization should involve stakeholder collaboration and take into account various perspectives, including business value and technical considerations. This ensures that all parties have a shared understanding of the trade-offs involved.
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.