A business analyst (BA) has executed the last planned workshop in a series in order to verify requirements. All issues have been logged in an issues register. What technique is used to manage and resolve the outstanding issues?
Section 10.29: Item Tracking in the BABOK Guide describes how item tracking is used to manage issues, actions, and defects. It provides a structured approach to follow up on outstanding items and ensures they are resolved as part of the requirements management process.