Exam CCBA topic 1 question 418 discussion

Actual exam question from IIBA's CCBA
Question #: 418
Topic #: 1
[All CCBA Questions]

A new contract requires a thorough level of documentation to be developed and maintained with planned phases of reviews and authorized sign offs. Which approach fits this contract?

  • A. Waterfall
  • B. Agile
  • C. Scrum
  • D. Iterative
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
keyss
4 days, 4 hours ago
Selected Answer: A
A. Waterfall
upvoted 1 times
...
17b7c4c
1 month, 1 week ago
Selected Answer: A
Section 2.1.4: Plan Business Analysis Approach describes how Waterfall is well-suited for projects with well-defined phases, extensive documentation needs, and formal review and sign-off processes. These aspects are crucial in regulated environments or contracts requiring strict adherence to documentation and approval.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.