A project to replace a financial system uses a waterfall methodology. Initially, meetings with the project subject matter experts (SMEs) were positive. As the project progressed through the requirements and design phases, the SMEs attended fewer meetings, resulting in a delay to the project build phase. What should the business analyst (BA) have done to prevent the delay?

  • A. Selected a different project methodology
  • B. Requested new SMEs participate in the project
  • C. Modified the governance structure
  • D. Engaged in consistent collaboration
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
17b7c4c
3 months ago
Selected Answer: D
Section 3.2: Elicitation and Collaboration emphasizes the importance of continuous stakeholder engagement throughout the project. This is particularly critical in a waterfall methodology, where delays in earlier phases can significantly impact later phases due to the linear progression of tasks.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago