Question #: 410
Topic #: 1
[All CCBA Questions]

A project team needs to maintain the traceability of requirements for a software system. Due to the large number of requirements, which of the following methods should the team use?

  • A. Use a requirements management tool
  • B. Create a requirements model
  • C. Maintain the requirements manually
  • D. Develop a database management system
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
keyss
1 month, 3 weeks ago
Selected Answer: A
A. Use a requirements management tool
upvoted 1 times
...
17b7c4c
3 months ago
Selected Answer: A
Section 5.1.5: Requirements Traceability suggests that tools and technology can be used to facilitate the traceability of requirements, especially in complex projects. A requirements management tool enables better organization, control, and visibility of requirements, which is essential when handling a large number of requirements.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago