Question #: 405
Topic #: 1
[All CCBA Questions]

A business analyst (BA) is defining constraints for a project. Which of the following is a valid constraint?

  • A. “The solution must be implemented in six (6) months.”
  • B. “The solution must increase sales by 20%.”
  • C. “The solution must promote workplace safety.”
  • D. “The solution must reduce support calls by 20%.”
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
keyss
4 days, 6 hours ago
Selected Answer: A
A. “The solution must be implemented in six (6) months.”
upvoted 1 times
...
17b7c4c
1 month, 1 week ago
Selected Answer: A
Section 6.2.4: Assess Current State and Define Future State Constraints discusses constraints as limitations or restrictions that impact the solution's scope or delivery. This includes factors like time, cost, and regulatory requirements that the project must work within.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...