An organization prefers to execute projects using an adaptive approach. However, the new project is much more complex than previously executed projects. What will the business analyst (BA) recommend?
B. Review current approach with key stakeholders.
Justification:
When a project is more complex than previous ones and the organization typically prefers an adaptive approach, the business analyst (BA) should recommend reviewing the current approach with key stakeholders. This allows the BA and stakeholders to assess whether the chosen adaptive approach is still suitable for the complexity of the project, or if adjustments need to be made, such as incorporating elements from a predictive approach to handle complexity.
Relevant Sections in BABOK:
Section 2.3.1: Business Analysis Approach highlights the need to evaluate the project’s complexity and tailor the approach accordingly. It emphasizes collaboration with stakeholders to assess and adjust approaches as required, ensuring the approach fits the context and complexity of the project.
upvoted 1 times
...
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
keyss
4 days, 7 hours ago17b7c4c
1 month, 2 weeks ago