The business analyst (BA) recommended a new application be rolled out in phases. After reviewing alternatives, the project sponsor agreed. What does the BA expect to achieve by this approach?
C. Maximize benefits
This aligns with the BABOK® Guide, specifically under Task 7.5: Recommend Actions to Increase Solution Value, which highlights that phased implementation is a strategy to maximize the value delivered to the organization by allowing early realization of benefits (see Section 7.5.4).
upvoted 1 times
...