A business analyst (BA) creates several use case scenarios to specify the requirements for a system. When the beta version of the system is released, there are problems because several important pieces of information are missing. What should the BA have done to avoid this situation?

  • A. Performed decision analysis
  • B. Identified assumptions
  • C. Prepared activity diagrams
  • D. Analyzed completeness
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
17b7c4c
3 months, 1 week ago
Selected Answer: D
In Section 5.3.2 (Requirements Analysis), the BABOK discusses the importance of ensuring that all requirements are complete and include all necessary details. Analyzing completeness is part of validating and verifying that the documented requirements fully capture the intended functionality and address all user needs.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago