Which of the following inputs of Monitor and Control Risks acquires information from performance measurements and evaluates it to provide variance analysis and forecasting?
Work performance information includes data gathered from performance measurements, such as project progress, status reports, and key performance indicators (KPIs). This information is evaluated to provide variance analysis, trend analysis, and forecasting in the “Monitor and Control Risks” process. It helps assess how well the project is performing compared to the plan and whether risks are materializing as expected.
B. Work performance information
In the Monitor and Control Risks process, work performance information is the input that acquires information from performance measurements and evaluates it to provide variance analysis and forecasting. This information helps assess the current status of risks, monitor their progress, and identify any emerging risks or changes in risk conditions. Therefore, option B is the correct choice.
upvoted 2 times
...
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
Nobita135
3 weeks, 1 day agoInzaghi78
2 months, 3 weeks ago