Actual exam question from IIBA's CBAP
Question #: 107
Topic #: 1
[All CBAP Questions]

You are the business analyst for your organization and are working with Sally, a project manager, for your organization. You and Sally are determining the cost of the labor, materials, equipment, and facilities in order to achieve the different solutions that have been proposed for an identified problem.
What is this process called?

  • A. Cost budgeting
  • B. Expert judgment
  • C. Rough order of magnitude cost estimating
  • D. Scoping the project costs
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
hieueddie
6 days, 16 hours ago
Selected Answer: C
• Rough Order of Magnitude (ROM): a high-level estimate, generally based on limited information, which may have a very wide confidence interval
upvoted 1 times
...
CBAPCohort6
2 months, 1 week ago
Selected Answer: C
C. Rough order of magnitude cost estimating This process involves estimating the costs of labor, materials, equipment, and facilities for the various proposed solutions to an identified problem. It is typically used in the early stages of project planning to provide a preliminary estimate of costs​.
upvoted 1 times
...
basmus12
2 months, 3 weeks ago
Selected Answer: C
In this scenario, it indicates an early and broad estimation, which aligns with ROM (Rough Order of magnitude) cost estimating. A. Cost budgeting happens later when a more detailed financial breakdown is needed. B. Expert judgment is a technique used in various stages, but it is not a cost estimation process in itself. D. Scoping the project costs is not a formal process term in project management.
upvoted 1 times
...
BA1002
4 months, 3 weeks ago
A. Cost budgeting
upvoted 1 times
...
flo16
6 months, 2 weeks ago
C. Rough order of magnitude cost estimating This type of cost estimation is typically performed early in the project to provide an approximate figure of the costs involved, often when there is limited information available about the project.
upvoted 1 times
...
Inzaghi78
8 months, 3 weeks ago
A. Cost budgeting The process of determining the cost of labor, materials, equipment, and facilities required to achieve different solutions proposed for an identified problem is known as cost budgeting. Cost budgeting involves estimating the costs associated with implementing the project scope, activities, and deliverables. This process helps in developing the project budget, which allocates resources to various project activities and components. Therefore, option A, cost budgeting, is the correct term for this process.
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago