Actual exam question from IIBA's CBAP
Question #: 253
Topic #: 1
[All CBAP Questions]

The ____, an output of the define scope process, does document the process and criteria for accepting completed products.

  • A. Statement of Work
  • B. Contract
  • C. Project scope statement
  • D. Project management plan
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
NgocThanh
1 week, 6 days ago
Selected Answer: C
The Project Scope Statement is an output of the Define Scope process. It documents the process and criteria for accepting completed products, including the project’s deliverables, acceptance criteria, exclusions, constraints, and assumptions. This statement provides a clear understanding of what the project will deliver and serves as a reference for project acceptance and validation.
upvoted 1 times
...
Rabbitsfoot
3 months, 3 weeks ago
Selected Answer: C
BABOK V3 Glossary - project scope: The work that must be performed to deliver a product, service, or result with the specified features and functions. A 'statement' of the project scope would answer the question.
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago