Question #: 465
Topic #: 1
[All CCBA Questions]

Before selecting a design solution, a company wants to ensure that stakeholder, solution, and transition requirements align to the business requirements and also that the design satisfies the requirements. What process is the business analyst (BA) completing?

  • A. Requirements Verification
  • B. Requirements Validation
  • C. Requirements Engineering
  • D. Requirements Elicitation
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
keyss
1 month, 3 weeks ago
Selected Answer: B
B. Requirements Validation
upvoted 1 times
...
hrk55
1 year ago
Selected Answer: B
B. Requirements Validation
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago