Exam CCBA topic 1 question 172 discussion

Actual exam question from IIBA's CCBA
Question #: 172
Topic #: 1
[All CCBA Questions]

An organization has selected a solution for a business need and the business analyst has elected to use the time boxing/budgeting technique for requirements prioritization. What is the time boxing/budgeting technique?

  • A. It's a method to prioritize requirements based on a pre-determined budget and/or a pre-determined deadline.
  • B. It's used when there are conflicting requirements that must be resolved quickly and cost efficiently.
  • C. It's a method to rank requirements in different boxes based on time, cost, risk, and need.
  • D. It's used to determine which requirements can be implemented fastest and for the least amount of cost.
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
keyss
2 weeks, 4 days ago
Selected Answer: A
pre-determined budget and/or a pre-determined deadline
upvoted 1 times
...
17b7c4c
1 month, 1 week ago
Selected Answer: A
BABOK Section 5.2.5: Prioritize Requirements, the time boxing/budgeting technique is used to prioritize requirements based on a fixed budget or timeline. In this approach, requirements are prioritized by identifying the most critical or valuable requirements that can be completed within a specified time frame or budget. This technique helps ensure that the project stays within constraints and delivers the most essential features first, maximizing value under given limitations.
upvoted 1 times
...
Moathov
11 months, 3 weeks ago
Selected Answer: A
A. It's a method to prioritize requirements based on a pre-determined budget and/or a pre-determined deadline.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...