The correct answer is C. As soon as a business need is identified.
Stakeholder analysis is typically performed early in the project lifecycle, as soon as a business need is identified. This is because stakeholders can have a significant impact on the project's success, and identifying them early on can help ensure that their needs and expectations are taken into account.
By performing stakeholder analysis at this stage, you can:
- Identify key stakeholders who will be impacted by the project
- Understand their interests, needs, and expectations
- Develop a plan to engage and communicate with them effectively
- Ensure that their concerns and issues are addressed throughout the project lifecycle
The other options are not correct because:
- A. As soon as the project charter is created: While the project charter may provide some information about stakeholders, it's not typically the trigger for stakeholder analysis.
- B. As soon as the project sponsor is named: The project sponsor is an important stakeholder, but stakeholder analysis should consider all relevant stakeholders, not just the sponsor.
- D. As soon as a business solution is identified: By this stage, the project may have already progressed too far, and stakeholder analysis may not be as effective in identifying and addressing stakeholder concerns.
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
KEN_ELELEGWU
2 weeks, 6 days agoKEN_ELELEGWU
2 weeks, 6 days agoChu2
6 months, 2 weeks agoRfcuenca
1 year ago