You are the business analyst for your organization. On your current project you'll be using the change-driven approach for defining requirements and gathering feedback. Which of the following statements best describes the change-driven approach?
A.
The change-driven approach favors defining requirements through experimentation.
B.
The change-driven approach does not define the requirements until after a solution for the problem has been identified.
C.
The change-driven approach favors defining requirements standardized templates.
D.
The change-driven approach favors defining requirements through team interaction.