Question #: 282
Topic #: 1
[All CCBA Questions]

You have been assigned as the Project Manager for a new project that involves the development of a new interface for your existing time management system.
You would like to plan the communications that need to be made during the project lifecycle. Which of the following would be a critical tool/technique to help in your communications planning?

  • A. RAM Chart
  • B. Affinity Diagram
  • C. Stakeholder Analysis
  • D. Text-Oriented Chart
Show Suggested Answer Hide Answer
Suggested Answer: Answer: B is incorrect. Affinity Diagram is a method of group creativity technique to collect requirements which allows large numbers of ideas to be sorted into 🗳️
Stakeholder Analysis involves identification of the stakeholders and classifying them based on their interest, influence, and involvement in the project. This enables the project manager to focus on the relationships necessary to ensure the success of the project by planning the communications properly. groups for review and analysis. This is generally used in Scope Management and is not applicable to this question. as tools in developing the Human Resource Plan. These are not applicable to this question.

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Cheburaators
4 months, 3 weeks ago
Selected Answer: C
Stakeholder Analysis
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago