Question #: 251
Topic #: 1
[All CCBA Questions]

In order to plan business analysis activities, you will need four inputs. Which one of the following inputs is not valid for this task?

  • A. Business analysis approach
  • B. Stakeholder tolerance for risk
  • C. Stakeholder list, roles, and responsibilities
  • D. Business analysis performance assessment
Show Suggested Answer Hide Answer
Suggested Answer: Answer: A, D, and C are incorrect. Following are the inputs in Plan Business Analysis Activities: 🗳️
Stakeholder tolerance for risk is not a valid input for planning business analysis activities.

Business Analysis Approach -
Business Analysis Performance Assessment

Organizational Process Assets -
Stakeholder List, Roles, and Responsibilities

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
17b7c4c
1 month, 1 week ago
Selected Answer: B
B. Stakeholder tolerance for risk
upvoted 1 times
...
Cheburaators
1 year, 3 months ago
Selected Answer: B
Stakeholder tolerance for risk
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.