exam questions

Exam CCBA All Questions

View all questions & answers for the CCBA exam

Exam CCBA topic 1 question 234 discussion

Actual exam question from IIBA's CCBA
Question #: 234
Topic #: 1
[All CCBA Questions]

An organization has two different solutions to grow its business. One project is worth $375,000 to the organization. The second project is worth $565,000 to the business. The organization can only do one of the projects and elects to do the second project for $565,000. What is the opportunity cost of this decision?

  • A. $190,000
  • B. $565,000
  • C. $375,000
  • D. $940,000
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
keyss
1 month, 1 week ago
Selected Answer: C
C.
upvoted 1 times
...
17b7c4c
2 months, 3 weeks ago
Selected Answer: C
C. $375,000
upvoted 1 times
...
Cheburaators
1 year, 4 months ago
Selected Answer: C
$375,000
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago