Suggested Answer:Answer: B is incorrect. Project charter is one of the inputs of the Identify Stakeholders process.🗳️
The Identify Stakeholders process identifies all people or organizations that are impacted by the project. It also documents relevant information regarding their interests, involvement, and impact on project success. Stakeholder register and stakeholder management strategy are outputs of this process.
The stakeholder register is the direct output of the Identify Stakeholders process. It documents details about identified stakeholders, including their roles, interests, influence, and communication preferences.
BABOK Reference (Chapter 2: Business Analysis Planning and Monitoring - Stakeholder Analysis):
The stakeholder register ensures all stakeholders are accounted for and their needs are understood, serving as a foundation for engagement and communication planning
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
teletee
2 weeks agoCheburaators
7 months, 1 week ago