In prioritizing requirements, which of the following factors include difficulty of implementing a requirement, or the likelihood that a requirement cannot deliver its potential value?
BABOK V3 Pg 88
Risk: the chance that the requirement cannot deliver the potential value, or
cannot be met at all. This may include many factors such as the difficulty of
implementing a requirement, or the chance that stakeholders will not
accept a solution component.