You have identified a task in your task list that cannot be completed until the inspector for the project signs off on the initial deliverables. The inspector's signoff on the initial deliverables is called what?
In project management, a dependency refers to a relationship between two tasks or activities where the completion of one task is dependent on the completion of another. In this context, the task on your list that cannot be completed until the inspector signs off on the initial deliverables is dependent on the inspector's action, making it a dependency.
C. Milestone
The inspector's signoff on the initial deliverables is referred to as a milestone. A milestone represents a significant point or event in a project, often used to mark the completion of a major phase or the achievement of a critical objective. In this case, the inspector's signoff is a crucial milestone that indicates the completion and approval of the initial deliverables, allowing the project to progress to the next phase or task.
In the context of the BABOK (Business Analysis Body of Knowledge) guide, the inspector's signoff on the initial deliverables would be considered a MILESTONE. A milestone represents a significant point in time within a project or business analysis process, and it often involves the completion of a major deliverable or the achievement of a key event. In this case, the inspector's signoff serves as a milestone indicating the completion and acceptance of the initial deliverables.
C .MILESTONE
The inspector's signoff on the initial deliverables is referred to as a "C. Milestone." In project management, a milestone represents a significant event or achievement that marks progress in a project, and the inspector's signoff is a critical milestone indicating the completion of the initial deliverables.
C. Milestone
In project management, a milestone is a significant event or point in time that marks the completion of a specific deliverable or phase of the project. It represents an important achievement and is often used to track progress and measure the project's success.
upvoted 1 times
...
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
Dmylitos
5 months agoGeorgian1994
7 months, 1 week agojeffreyokonkwo_
8 months, 4 weeks agoRabbitsfoot
5 months, 1 week agoangela111
9 months, 3 weeks agoteehmama
9 months, 3 weeks agocsg2023
10 months, 1 week agocert_diwana
11 months, 1 week agoGroup02
1 year, 1 month ago