Exam CCBA topic 1 question 9 discussion

Actual exam question from IIBA's CCBA
Question #: 9
Topic #: 1
[All CCBA Questions]

You are the business analyst for a large software development project. There are several issues that must be resolved by certain dates or the problem will prevent the project from advancing. What technique can you use to track problems with the requirements?

  • A. Issue tracking
  • B. RTM
  • C. Problem tracking
  • D. Baselining
Show Suggested Answer Hide Answer
Suggested Answer: Answer: D is incorrect. Baselining the requirements does not track problems but creates a standard set of requirements that deliverables may be compared 🗳️
The technique you'll use is simply problem tracking. This technique allows the business analyst to manage any issues identified within requirements by stakeholders and to ensure that those issues are resolved.
Problem tracking allows the business analyst to manage any issues identified within requirements by stakeholders and to ensure that those issues are resolved. It provides an organized approach to tracking, management, and resolution of defects, issues, problems, and risks throughout business analysis activities.
Management of issues is important so that they can be resolved in a timely manner to ensure success. against.

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
teletee
4 days, 6 hours ago
Selected Answer: C
According to the BABOK Guide (Chapter 5: Requirements Life Cycle Management - Maintain Requirements), Problem Tracking is a business analysis technique used to: Identify, track, and resolve issues that may affect requirements. Assign ownership and prioritize problems based on their impact. Ensure that issues are resolved within the required timeframe to prevent project delays. Since the question mentions several issues that must be resolved by certain dates, Problem Tracking is the most appropriate technique.
upvoted 1 times
...
keyss
2 months, 3 weeks ago
According to the BABOK- The answer would be Item Tracking Technique - 10.26 -Item Tracking Purpose - Item tracking is used to capture and assign responsibility for issues and stakeholder concerns that pose an impact to the solution.
upvoted 1 times
...
MrAceOfficial
3 months ago
The answer is Problem Tracking. RTM is Requirement Traceability Matrix used to trace requirements throughout the project lifecycle.
upvoted 1 times
...
JennKOH
1 year, 5 months ago
Selected Answer: B
RTM = Requirements Traceability Matrix
upvoted 1 times
...
Stella9711
1 year, 10 months ago
it's RTM
upvoted 1 times
...
Thunderbird35
1 year, 11 months ago
The answer is RTM
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago