What is the most important risk in determining the validity of construction delay claims?

  • A. Contractor claims may be submitted prior to completion of the work.
  • B. Contractor claims may include costs considered in the fixed-price portion of the work.
  • C. Contractor claims may include subcontractor estimates of balances due to the subcontractor.
  • D. Contractor claims may be understated.
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
JamalAli
3 months, 3 weeks ago
This is about contract types. In general delays are to be paid and in another case it should be fixed rate then payment for delays is not reasonable. So, there could be fixious or fraud payment.
upvoted 2 times
...
KonradK
4 months, 2 weeks ago
Can some explain why B? thanks
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago