Which of the following statements regarding program change management is not correct?

  • A. The goal of the change management process is to sustain and improve organizational operations.
  • B. The degree of risk associated with a proposed change determines if the change request requires authorization.
  • C. In order to protect the production environment, changes must be managed in a repeatable, defined, and predictable manner.
  • D. All changes should be tested in a non-production environment before migrating to the production environment.
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
64121de
1 week, 5 days ago
Selected Answer: B
Do approval is always required for any changes?
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago