An internal auditor wanted to determine whether the organization's 200 employees are charging their work hours accurately to the correct project The internal auditor selected a sample of 30 employee time reports for testing. Based on the testing, the internal auditor determined the following:
- 5 time reports were incorrect.
- 21 time reports were correct.
- 4 time reports were not supported.
Which of the following conclusions is appropriate?