An internal audit manager is planning a contract compliance audit. Which of the following should be done prior to developing the audit work program?

  • A. Select a sample of invoices for substantive testing.
  • B. Review the contract for evidence of authorization.
  • C. Document underlying reasons for noncompliance.
  • D. Assess the inherent risk of paying duplicate invoices.
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
AFD22
2 days, 11 hours ago
Selected Answer: B
Review the contract for evidence of authorization.
upvoted 1 times
...
Elvoo
2 months ago
Why not B?
upvoted 2 times
...
emtofid
3 months, 3 weeks ago
Selected Answer: C
Select a sample of invoices for substantive testing is part of audit execution, which would occur after the work program has been developed.
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago