At what stage of project integration management would a project manager and project management team typically coordinate the various technical and organizational interfaces that exist in the project?
The stage at which the project manager and team coordinate technical and organizational interfaces is during project plan execution because this is when the actual work is being carried out and different teams, systems, and stakeholders must be aligned.
I'm thinking B because during this stage, the project manager and team work on putting the project plan into action by executing the tasks and activities outlined in the plan. This involves coordinating with different stakeholders, including technical experts and other departments, to ensure that the project progresses smoothly.
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
emtofid
1 month agoElvin
6 months, 1 week agoElvin
6 months agoKonradK
5 months, 4 weeks ago