An organization was forced to stop production unexpectedly, as raw materials could not be delivered due to a military conflict in the region. Which of the following plans have most likely failed to support the organization?
Contingency plans are designed to prepare an organization for unexpected disruptions, such as supply chain failures due to military conflicts, natural disasters, or other crises. Since production had to stop unexpectedly, it suggests that the organization did not have an effective contingency plan in place to address supply chain disruptions by identifying alternative suppliers, stockpiling critical materials, or adjusting production strategies.
A. Just-in-time delivery plans focus on minimizing inventory by receiving materials only when needed, but they are not designed to handle major disruptions.
Shouldn't it be C for contingency plans as military conflict impacted delivery of materials
upvoted 1 times
...
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
Elvoo
2 days, 6 hours agoemtofid
2 weeks, 2 days agoKonradK
6 months, 4 weeks agoKonradK
7 months ago