A company is using Process Flow Control to ensure the tasks are done in the proper order. By default, which status indicated the next task to be worked on?
Answer should be C. Question is " which status indicated the next task to be worked on?"
Reference: https://www.ibm.com/support/pages/work-order-flow-control-release-71
-Go to Task Work order of Task 10
-From action menu try to change status to “Complete”
-Result: Task 20 and task 30 would now change to “In Progress” status (These are the tasks to be worked on)