An approved work order has been assigned an incorrect job plan.
How do you correct this?

  • A. Change the Job Plan Revision to the correct revision.
  • B. Clear the Job Plan field and enter the correct job plan.
  • C. Create a Follow-up work order with the correct job plan.
  • D. Select Remove Work Plan from the More Actions menu and enter the correct job plan.
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
beanz998
2 years, 1 month ago
C is corect. You can't remove WO tasks once a work order is approved. This action is required to remove the work plan.
upvoted 1 times
...
fdeghadi
2 years, 3 months ago
C is the correct as Job Plan Revise will not help and also remove Job Plan unless there are org Setup for Edit Work Role
upvoted 2 times
...
lucafranco
2 years, 11 months ago
The only possible correct anwer should be C. A is wrong, Job Plan Revision field is always read only B is wrong Job Plan field is read only for approved work orders. D. is wrong, Remove Work Plan from the More Actions generate the error: BMXAA4672E - Work plan must be editable to remove it.
upvoted 4 times
...
everwelwisher
3 years, 3 months ago
D is the correct one
upvoted 1 times
...
everwelwisher
3 years, 3 months ago
Answer D @lavosier Follow up work order is used once the work order has completed and additional work is required on the same work order
upvoted 1 times
...
Sindhu_Tyro
3 years, 11 months ago
C is correct
upvoted 1 times
...
Sindhu_Tyro
3 years, 11 months ago
i think answer is B as Jobplan field on workorder object will be editable unless specified to be read only.
upvoted 1 times
...
Lavoisier
4 years, 2 months ago
I think the answer is C "Create a follow-up work order..." because it is not possible to remove task on an Appr work order. Since remove Job Plan will remove all task, the answer D is not correct https://www.ibm.com/support/knowledgecenter/SSBLW8/com.ibm.mbs.doc/wotrack/c_wo_mgmt_plans.html
upvoted 3 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...