Question #: 141
Topic #: 1
[All C2010-555 Questions]

A technician has completed a job and observed that more work is needed on the same asset. A new record is required to have the same asset, location and GL account. What action needs to be taken?

  • A. Select Create Follow-up action from the completed work order
  • B. Select Create Work Order action from the completed work order
  • C. Select Create Work Package action from the completed work order
  • D. Click on the Plans tab, and add a new child work order from the completed work order
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️
Reference:
https://www.ibm.com/support/knowledgecenter/pt-br/SSANHD_7.6.0/com.ibm.mbs.doc/wotrack/c_record_relationships_wos.html

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Yiorgos
3 years, 10 months ago
The correct answer is B There is no Create Follow up Work Order. The right action is Create Work Order which produces a Follow up work order
upvoted 1 times
...
stevo1091
3 years, 11 months ago
Answer A is correct (from the source provided): When you create follow-up work orders, the asset, location, and general ledger account are copied from the originating work order to the follow-up work order.
upvoted 1 times
...
MaxComp
4 years, 4 months ago
Answer B
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...