Exam C2010-555 topic 1 question 129 discussion

Actual exam question from IBM's C2010-555
Question #: 129
Topic #: 1
[All C2010-555 Questions]

A company wants to issue a tool with an hourly rate to a work order. Which applications can be used to do this?

  • A. Inventory | Tools
  • B. Stocked Tools, Inventory
  • C. Tools, Work Order Tracking
  • D. Stocked Tools, Work Order Tracking
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️
Reference:
https://www-01.ibm.com/support/docview.wss?uid=swg21672597

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
everwelwisher
3 years, 3 months ago
Answer D is correct
upvoted 1 times
...
Yiorgos
3 years, 10 months ago
The correct answer is A. The question is only asking (poorly!) how to specify an hourly rate and not necessarily how to issue it after you set up the rate.
upvoted 1 times
...
Vahee
4 years, 4 months ago
Answer is D.
upvoted 4 times
...
elma93
4 years, 4 months ago
Set the Hourly Rate for a Tool: 1. Go To Inventory | Tools 2. Open the tool record 3. Select Action | Tool/Organization Details 4. In the Tool Rate field enter an hourly cost for this tool's usage
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...