An administrator want to create a time based escalation point to evaluate to 30 days in the future.
What is the correct value to use in the Elapsed Time Interval field along with the Elapsed Time Attribute?

  • A. Today + 30
  • B. Sysdate + 30
  • C. +30 (positive 30)
  • D. -30 (negative 30)
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
TanweerAl
Highly Voted 4 years, 4 months ago
Answer should be D. -30 https://www.ibm.com/support/knowledgecenter/SSBLW8/com.ibm.mbs.doc/escalation/t_defining_escalation_pts.html
upvoted 6 times
...
fdeghadi
Most Recent 2 years, 3 months ago
the correct is D as A negative time period for future
upvoted 1 times
...
Deepthi28
3 years, 1 month ago
Answer D
upvoted 1 times
...
MaxComp
4 years, 4 months ago
Answer D
upvoted 3 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other