Exam C2010-555 topic 1 question 62 discussion

Actual exam question from IBM's C2010-555
Question #: 62
Topic #: 1
[All C2010-555 Questions]

A company has a work order with 50 separate tasks and 40 of the tasks have been completed. The company would like the remaining 10 tasks grouped with a new parent work order.
Which option will group the tasks?

  • A. Select the task work orders and Create Work Package.
  • B. Select the task work orders Create Job Plan from Work Plan.
  • C. Create a new work order and add the task work orders on the Plans tab.
  • D. Create a new work order and add the child work orders on the Plans tab.
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
fdeghadi
2 years, 3 months ago
Selected Answer: A
Create Work Package Select Action
upvoted 1 times
...
tomben_eu
4 years ago
A: https://www.ibm.com/support/knowledgecenter/en/SSLKT6_7.6.1.1/com.ibm.mbs.doc/wotrack/c_work_pkgs.html
upvoted 1 times
...
joe12398
4 years, 8 months ago
the answer is A
upvoted 3 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...