In the Work Order Tracking application, a Work Order is generated from a Preventive Maintenance (PM) record. How is the target finish date calculated?

  • A. the Job Plan finish date
  • B. the PM target finish date
  • C. the Work Order target start date + the Job Plan duration
  • D. the Job Plan start date + the Job Plan duration
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
fdeghadi
10 months, 3 weeks ago
d is wrong Job Plan has no date, correct answer is C
upvoted 1 times
...
Clem2
1 year ago
Selected Answer: C
C is the correct option
upvoted 2 times
...
stefun75
1 year ago
Selected Answer: C
Teh correct answer is C. the Work Order target start date + the Job Plan duration. The Joblan has no Start en finish dates The pm has no target finish date
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...