Actual exam question from GAQM's CSM-001
Question #: 55
Topic #: 1
[All CSM-001 Questions]

As the Sprint planning progresses, the workload has grown beyond the development team's capacity. Which action makes most sense for the Team?

  • A. Work overtime for the Sprint
  • B. Collaborate with the Product Owner and potentially remove or change items
  • C. Cancel the Sprint
  • D. Star the Sprint and recruit additional team members
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
patitos
2 months, 1 week ago
Answer is B
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago