Question #: 51
Topic #: 1
[All CSM-001 Questions]

The correct sequence of events in using Scrum framework is as follows:

  • A. Sprint Planning, Sprint, Sprint Retrospective, Daily Scrum, and Sprint Review
  • B. Sprint Planning, Sprint, Daily Scrum, Sprint Review, and Sprint Retrospective
  • C. Sprint Planning, Sprint, Sprint Retrospective, Daily Scrum, and Sprint Review
  • D. Sprint Planning, Daily Scrum, Sprint, Sprint Review, and Sprint Retrospective
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Ranita
2 weeks, 3 days ago
Selected Answer: B
C is correct
upvoted 1 times
...
patitos
8 months, 1 week ago
Answer is C
upvoted 1 times
MRabi
7 months, 2 weeks ago
I disagree
upvoted 1 times
...
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago