Which of the following statements best explains what the term Sprint means in Scrum?

  • A. A sprint is a specific amount of days for a team to test and resolve any issues prior to product release or shipment
  • B. A sprint is a specific amount of days for a team to work at a sustainable pace to finish select work.
  • C. A sprint is an agreed upon period of time for team members to select individual items from the product backlog to work on.
  • D. A sprint is a specific amount of days for a team to work as many hours as needed to finish assigned work
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
san28
2 months, 4 weeks ago
Selected Answer: B
B has the best description.
upvoted 1 times
...
AG001
4 months, 1 week ago
B is correct
upvoted 1 times
...
patitos
1 year, 2 months ago
Answer is B
upvoted 1 times
...
DenisR
1 year, 8 months ago
Could you please double check the grammar on this question? The correct sentence should be ".. a specific number of days" not ".. a specific amount of days"
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago