A. Total Days in Sprint
A Sprint Burn down Chart typically does not reflect the total days in the Sprint. It focuses on the progress of work in terms of either the number of tasks or the work hours remaining to complete the Sprint Backlog items. The chart displays the relationship between the amount of work that needs to be completed and the time that has passed during the Sprint. It helps the Scrum Team and stakeholders visualize how the work is being completed over the course of the Sprint and whether the team is on track to meet the Sprint Goal.
The burndown chart consists of
X Axis: Indicates time, usually in days
Y Axis: Indicates remaining work to be done in a sprint and can be represented by either number of tasks or remaining
Progress Line: Indicates the team progress through the sprint
Guideline: The projected estimate that is drawn downwards from top left to bottom right on the graph.
"Unlike the Sprint Burndown Chart which shows the amount of work
remaining, the Sprint Burnup Chart depicts the work completed as part of the Sprint" - SBOK 9.6.3.2
upvoted 1 times
...
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
AYOR2
4 months, 1 week agobrightblue
4 months, 2 weeks agoKamalindya
3 years ago