exam questions

Exam CSM-001 All Questions

View all questions & answers for the CSM-001 exam

Exam CSM-001 topic 1 question 38 discussion

Actual exam question from GAQM's CSM-001
Question #: 38
Topic #: 1
[All CSM-001 Questions]

Which of the following is not reflected in a Sprint Burn down Chart?

  • A. Total Days in Sprint
  • B. Number of Tasks Remaining
  • C. Day of Sprint
  • D. Work Hours Remaining
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
AYOR2
4 months, 1 week ago
A. Total Days in Sprint A Sprint Burn down Chart typically does not reflect the total days in the Sprint. It focuses on the progress of work in terms of either the number of tasks or the work hours remaining to complete the Sprint Backlog items. The chart displays the relationship between the amount of work that needs to be completed and the time that has passed during the Sprint. It helps the Scrum Team and stakeholders visualize how the work is being completed over the course of the Sprint and whether the team is on track to meet the Sprint Goal.
upvoted 1 times
...
brightblue
4 months, 2 weeks ago
Selected Answer: D
The burndown chart consists of X Axis: Indicates time, usually in days Y Axis: Indicates remaining work to be done in a sprint and can be represented by either number of tasks or remaining Progress Line: Indicates the team progress through the sprint Guideline: The projected estimate that is drawn downwards from top left to bottom right on the graph.
upvoted 1 times
...
Kamalindya
3 years ago
"Unlike the Sprint Burndown Chart which shows the amount of work remaining, the Sprint Burnup Chart depicts the work completed as part of the Sprint" - SBOK 9.6.3.2
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago