The scrum master protects the team as a Servant-Leader so they can concentrate on the task at hand, the organisation of the the Product Backlog is solely the Product owner, the scrum master is involved with the sprint backlog only, the answer here is A
One of scrum master's responsibility is to shield team from external interference, any priority change should be from PO. The right answer should be A.