The scrum master protects the team as a Servant-Leader so they can concentrate on the task at hand, the organisation of the the Product Backlog is solely the Product owner, the scrum master is involved with the sprint backlog only, the answer here is A
One of scrum master's responsibility is to shield team from external interference, any priority change should be from PO. The right answer should be A.
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
Jazza
Highly Voted 3 years, 6 months agoSnownoodles
Highly Voted 3 years, 9 months agoMi_Windsor
Most Recent 5 months, 3 weeks agoMikhil16
9 months agoAG001
10 months, 1 week agohwuanghu
11 months agoRanita
1 year agonicesiuhung
2 years, 1 month agoaktheraja
3 years, 8 months ago