exam questions

Exam CSM-001 All Questions

View all questions & answers for the CSM-001 exam

Exam CSM-001 topic 1 question 36 discussion

Actual exam question from GAQM's CSM-001
Question #: 36
Topic #: 1
[All CSM-001 Questions]

You are the Scrum Master. The Sprint will complete in two days. Each day of the Sprint is equivalent to 8 hours. The team has just enough time to complete all tasks in the remaining 16 hours with the exception of three tasks. Of these three tasks, two tasks (a total of 6 hours) are required to complete one Product Backlog item and one task (an estimate of 2 hours) is required to complete another Product Backlog item. How should the development team handle the remaining three tasks?

  • A. The development team should negotiate with the Product Owner on the definition of "done".
  • B. The development team should work the extra 8 hours to complete their commitment to the Product Owner
  • C. The development team should place the two Product Backlog items back onto the Product Backlog
  • D. The development team should keep the three tasks on the Sprint Backlog for the next Sprint and complete those tasks first
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Roygabib
4 months, 1 week ago
A is the correct answer
upvoted 1 times
...
meg002
6 months, 2 weeks ago
Selected Answer: C
Answer is C. Team should return any uncompleted Product Backlog Items to the Product Backlog. Business priorities may have changed, and the Product Owner may choose to re-order the Product Backlog so that this item is lower on the list than it was previously.
upvoted 2 times
...
mith88
12 months ago
would the answer not be D, as the team will work on the unfinished tasks in the new sprint?
upvoted 1 times
...
patitos
1 year, 3 months ago
Answer is D..This task is already extimated meaning it should already in the sprintbacklog since No urgency applies..Then the Dev team should leave it for next sprint rather than affect the velocity of the team
upvoted 1 times
...
Abhyag
1 year, 7 months ago
Development team can't place item back to Product Log without discussing it with PO. Apt answer seems to be A
upvoted 1 times
...
Man4444
1 year, 7 months ago
Selected Answer: C
correct answer is C
upvoted 1 times
...
nicesiuhung
1 year, 8 months ago
answer is C
upvoted 1 times
...
StillPatient
3 years ago
The correct answer is C
upvoted 3 times
...
aktheraja
3 years, 3 months ago
A: done definition decided by PO
upvoted 2 times
...
Pooja
4 years, 2 months ago
correct answer C
upvoted 4 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago