You are the Scrum Master and your Development Team of 6 members has completed six Sprints with the following information:

Sprint 1: 10 pontos -

Sprint 2: 11 pontos -

Sprint 3: 15 pontos -

Sprint 4: 14 pontos -

Sprint 5: 15 pontos -

Sprint 6: 10 pontos -
The remaining story points for product development total 42. What is the approximate number of Sprint required to complete product development?

  • A. 6
  • B. 5
  • C. 4
  • D. 3
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
AYOR2
4 months, 1 week ago
The total completed story points from the first six sprints is: 10 + 11 + 15 + 14 + 15 + 10 = 75. The remaining story points are: 42. Adding the completed and remaining story points: 75 + 42 = 117. Now, to calculate the average story points per Sprint: 117 (total story points) / 6 (number of completed sprints) = 19.5. So, each Sprint, on average, has covered 19.5 story points. To determine the approximate number of Sprints required to complete the remaining 42 story points: 42 (remaining story points) / 19.5 (average story points per Sprint) ≈ 2.15. Since you can't have a fraction of a Sprint, rounding up gives you approximately 3 Sprints. So, the correct answer is: D. 3
upvoted 2 times
...
Vin_Cho
8 months, 3 weeks ago
as we are mentioning something which is by definition unpredictable, best approach is to use montecarlo simulation. Average or last sprint is not giving any good prediction. So can be several answers
upvoted 1 times
...
hereisayan
1 year, 8 months ago
considering the velocity of team based on past sprints it should be 4 only
upvoted 3 times
...
patitos
1 year, 8 months ago
Answer is B
upvoted 1 times
...
nicesiuhung
2 years, 1 month ago
C is correct answer
upvoted 1 times
...
moon_lee
3 years, 3 months ago
Should be B: i.e., 5 because - minimum that can be done in a sprint is 10. Hence for 42, atleast 5 sprints needed (assuming least per sprint is 10)
upvoted 4 times
nakshi
2 years, 2 months ago
how did u derive minimum that can be done in a sprint is 10? v shud be taking of past delivered sprints. so its 75/6=12.5
upvoted 3 times
...
...
zhannamil
3 years, 5 months ago
The correct answer is C (4 Sprints): 75/6=12.5 ; 42/12.5= 3.36 should be rounded to 4
upvoted 1 times
...
aktheraja
3 years, 8 months ago
B; This will be based on the worst case scenario. That is, the least pontos. so 42/10=4.2 and to nearest whole number = 5.
upvoted 3 times
...
Pooja
4 years, 7 months ago
correct answer is c i.e 4 sprints
upvoted 2 times
Ediye
4 years, 6 months ago
Could you please explain this? i'm stuck on it. Thanks
upvoted 2 times
Nithya
4 years, 5 months ago
Average work done in 6 sprints - 70/6 = 11.6 rounding off to 12. remaining backlog - 42. # of sprints required 42/12 = 3.5 rounded to 4
upvoted 6 times
...
...
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago