exam questions

Exam CSM-001 All Questions

View all questions & answers for the CSM-001 exam

Exam CSM-001 topic 1 question 8 discussion

Actual exam question from GAQM's CSM-001
Question #: 8
Topic #: 1
[All CSM-001 Questions]

Why does Scrum prevent Product Owners from changing Product Backlog items that are being worked on during the Sprint?

  • A. The development team cannot meet their Sprint commitment to complete work if requirements are changing
  • B. A Sprint cycle is not enough time for senior management review and approve changes
  • C. This forces Product Owners to focus on what is really important for the team to develop.
  • D. The development team must be able to limit the Product Owner authority
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Mi_Windsor
5 months ago
A is the correct answer
upvoted 1 times
...
Kylecyx
5 months, 1 week ago
A is the correct answer
upvoted 1 times
...
san28
9 months ago
Selected Answer: C
C is correct.
upvoted 1 times
...
Mikhil16
9 months ago
A should be the right answer
upvoted 1 times
...
AG001
10 months, 1 week ago
A should be the answer
upvoted 1 times
...
Lorrenzom
4 years, 1 month ago
C is the most correct ,Any changes that arises in the middle of the sprint should be added into the next sprint
upvoted 1 times
...
Pooja
4 years, 7 months ago
Answer should be A
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago