In the book "Managing Successful projects with Prince2", pg. 359 there is a table regarding check list of the process of "Authorize Initiation" which is part of Directing a project.
The checklist has a point:
"Has the project board approved the initiation stage plan? Specifically, has it:
obtained or committed the resources needed by the stage plan for the initiation stage?"
So, shouldn't the answer be D - Directing a project?