Which process provides the Project Board with the information it requires in order to commit resources to the project?

  • A. Managing Product Delivery
  • B. Initiating a Project
  • C. Controlling a Stage
  • D. Directing a Project
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Eleftheriia
2 years, 9 months ago
In the book "Managing Successful projects with Prince2", pg. 359 there is a table regarding check list of the process of "Authorize Initiation" which is part of Directing a project. The checklist has a point: "Has the project board approved the initiation stage plan? Specifically, has it: obtained or committed the resources needed by the stage plan for the initiation stage?" So, shouldn't the answer be D - Directing a project?
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...